Qatar General Electricity and Water Corporation "KAHRAMAA" has inaugurated "Ain Sinan" power substation with the aim of raising the capacity and efficiency of the electrical transmission network, in accordance with the highest standards of security and safety, at a cost of QR70.3m.
Ain Sinan substation is fed from the main "Kaaban" substation, and the new substation, with a voltage of 132/11 kV, supplies electric power to the surrounding residential areas, and is equipped with two transformers of 40 megavolt-amperes, in addition to overhead lines with a length of 13,623 km.
The opening of this substation comes as part of the continuous efforts of KAHRAMAA to provide services according to the highest standards of reliability in its electrical network, in line with the best international standards and in accordance with the local requirements, by using an advanced protection system linked to the fiber-optic network of control switches with a voltage of 132/11 kV, with the aim of raising the level of protection on network feeders.
Source: Government of Qatar